Mount Curve Watermain Project

Oct. 22 Project Update

Mount Curve Watermain Project MapProject Summary

The City is lining the existing watermain pipe near Mount Curve and Olympia Drive to eliminate the need for emergency repairs in the area. Work will be completed using Cured in Place Pipe (CIPP) lining, which limits the street disturbance needed to repair the aging watermain.

Mount Curve Road and Olympia Drive will be open during the project, but traffic control will be in place while crews are working. 

Water service to homes will be provided throughout construction. However, planned disruptions will be required during certain activities. Affected residents will be notified prior to any impacts. 

Mount Curve Watermain Project Map [PDF]

Timeline

Valve and hydrant repairs to prepare for the project began in late July 2024. Work is expected to be complete in late October.

 Project Phases  
 Sept. 3–19       Watermain bypass setup, testing and connection
 Sept. 20–Oct. 15  Watermain lining and testing
 Oct. 15–31  Paving and restoration
Project Contacts

Free viewers are required for some of the attached documents.
They can be downloaded by clicking on the icons below.

Acrobat Reader Download Acrobat Reader Windows Media Player Download Windows Media Player Word Viewer Download Word Viewer Excel Viewer Download Excel Viewer PowerPoint Viewer Download PowerPoint Viewer