City of Eden Prairie
Home MenuMount Curve Watermain Project
Project Summary
The City is lining the existing watermain pipe near Mount Curve and Olympia Drive to eliminate the need for emergency repairs in the area. Work will be completed using Cured in Place Pipe (CIPP) lining, which limits the street disturbance needed to repair the aging watermain.
Mount Curve Road and Olympia Drive will be open during the project, but traffic control will be in place while crews are working.
Water service to homes will be provided throughout construction. However, planned disruptions will be required during certain activities. Affected residents will be notified prior to any impacts.
Mount Curve Watermain Project Map [PDF]
Timeline
Valve and hydrant repairs to prepare for the project began in late July 2024. Work is expected to be complete in late October.
Project Phases | |
Sept. 3–19 | Watermain bypass setup, testing and connection |
Sept. 20–Oct. 15 | Watermain lining and testing |
Oct. 15–31 | Paving and restoration |