In partnership with the Minnesota Department of Transportation, the City of Eden Prairie is painting the bridge fascia beams on the following bridges along Highway 212:

  • Westbound Highway 5 bridge over Wallace Road
  • Mitchell Road bridge over Highway 212
  • Prairie Center Drive bridge over Highway 212
  • Northbound and southbound I-494 bridges over Highway 212

Click here to see a map showing the location of the bridges to be painted. [PDF]

Weather dependent, the project is scheduled to be completed in four consecutive days starting Tuesday, June 21. The following is a summary of how the work is scheduled to proceed and the associated traffic impacts. Delays along Highway 212 should be expected. Please use caution in traveling through the work zone.

TUESDAY NIGHT (JUNE 21–22)
Wallace Road bridge

  •  9 p.m.–5 a.m.  Closure of Wallace Road between Highway 212 ramps and Venture Lane

WEDNESDAY NIGHT (JUNE 22–23)
Southern portions of Mitchell Road, Prairie Center Drive and I-494 bridges

  • 7 p.m.–5 a.m.    Lane restrictions for eastbound Highway 212 between Wallace Road and Valley View Road
  • 10 p.m.–5 a.m.  Closure of southbound I-494 loop ramp to eastbound Highway 212 (detour will be marked)
  • 10 p.m.–5 a.m.  Closure of on-ramp from Prairie Center Drive to eastbound Highway 212 (detour will be marked)

THURSDAY NIGHT (JUNE 23–24)
Central portions of Mitchell Road, Prairie Center Drive and I-494 bridges

  • 7 p.m.–5 a.m.  Lane restrictions for eastbound and westbound Highway 212 between Wallace Road and Valley View Road

FRIDAY NIGHT (JUNE 24–25)
Northern portion of Mitchell Road, Prairie Center Drive and I-494 bridges

  • 7 p.m.–5 a.m.    Lane restrictions for westbound Highway 212 between Wallace Road and Valley View Road
  • 10 p.m.–5 a.m.  Closure of northbound I-494 loop ramp to westbound Highway 212 (detour will be marked)
  • 10 p.m.–5 a.m.  Closure of off-ramp from westbound Highway 212 to Prairie Center Drive (detour will be marked)